2018-01 Street Panels

Overall Percent Complete

10%

2018-01-Timeline

Status: Groundbreaking ceremony was held on March 30, 2019.  Construction commence on April 1, 2019.  Contractor has completed demolition of half of Horizon Drive and has installed driveway culverts.  Demolition of half of Summer Place is scheduled to start on April 30, 2019.

50.118 Street Panel Replacement:

Replacement and restoration of roadway panels.

50.83 C-4 Horizon Drive & Parallel Lot-Line Swale:

Improve/clean and restore approximately 2,700 linear feet of bar ditch (swale) on Horizon Drive and Parallel Lot-Line Swale at the rear of the properties between Horizon Drive and Summer Place.

50.84 C-5 Skyline Drive Swale:

Improve/clean and restore the bar ditch (swale) on Skyline Drive.

Area Impacted:

50-118