2018-06 City Facilities - HVAC/Boiler/Chiller Upgrades

Overall Percent Complete

15%

2018-06Timeline

Status: Equipment in Fabrication 80%

60.01 New Boiler:

Replacement of Boiler in Police Station

60.02 New Chiller:

Replacement of Chiller in Police Station

40.06 New Boiler:

Replacement of Boiler in Fire Station

40.07 New Chiller:

Replacement of Chiller in Fire Station

80.1 HVAC:

Replacement of two rooftop AC units at the Murphy Activities Center